Sisk – TANG Bridge

DPL Fabrications - Innovation and Sustainability

Case Study Details

12 Months
150 Tonne
£1 Million

Project Overview

DPL Fabrications were appointed by John Sisk & Sons at the concept stage of design to develop a practical and buildable solution for a steel demountable bridge on the Protos Phase 2 Project. The structure was required to span 52 metres across three spans, traversing a stream and critical national infrastructure assets. The Client’s brief demanded a robust, low-maintenance solution while ensuring future access to buried services in the event of an emergency.

Scope of Work

  • Design Development – Early engagement to provide specialist input into the design of a fully demountable bridge.
  • Fabrication & Supply – Manufacture of the steel bridge to the required execution standards.
  • Installation – Full site installation, including bearings and connection systems.

Demonstrated Capabilities

  • Collaboration with project stakeholders and consultants from the earliest stage.
  • Specialist knowledge in demountable steel structures.
  • Expertise in fabrication and installation under Execution Class 3 requirements.
  • Delivery within critical timeframes to meet project milestones.

Solution & Outcome

Through early collaboration with Gravitate Consulting Ltd, DPL combined design and construction expertise to deliver a bridge solution that was both innovative and practical.

The key outcomes included:

  • Fully Demountable Design – The bridge can be dismantled within 48 hours, enabling stakeholder access to underground services with plant and equipment during emergencies.
  • Durability & Cost Efficiency – Use of weathering steel to reduce long-term maintenance costs.
  • Structural Integrity – Incorporation of spherical bearings to manage movement during service life.
  • Quality & Reliability – Use of tension control bolts to ensure consistent quality and meet durability requirements.

Key Takeaways

  • Early engagement with contractors and consultants can significantly improve design practicality and buildability.
  • Demountable steel solutions provide long-term adaptability for infrastructure projects where stakeholder access is critical.
  • The use of weathering steel and advanced connection technology offers clients reduced maintenance costs and improved asset performance.
  • DPL’s collaborative and user-friendly approach ensures efficient project delivery and added value for clients.

Looking for innovative steel solutions? Contact us.

Testimonials

  • Bill Wellings

    Commercial Manager

    DPL brought their extensive structural steel knowledge to the project, providing Sisk with a fully buildable solution that met the Client’s requirements. They worked collaboratively from the concept stage through to installation, ensuring the bridge was fabricated and delivered to the highest standard. Their proactive and user-friendly approach helped simplify a technically challenging scheme, delivering real value for money while meeting critical programme deadlines